position: EnglishChannel  > InnovationChina> Sci-tech Resolves Dam Crack Dilemma

Sci-tech Resolves Dam Crack Dilemma

Source: Science and Technology Daily | 2025-03-06 18:15:24 | Author: WANG Jing

Located at the junction of Baiyu county in southwest China's Sichuan province and Konjo county in Xizang autonomous region, a world-renowned ultra-high arch dam project — the Yebatan Hydropower Station — is currently buzzing with construction fervor on the upper reaches of the Jinsha River.

"Cracks are a tricky problem in the process of concrete dam pouring," said Du Guangyuan, director of the engineering management department at Yebatan Branch of the Huadian Jinsha River Upstream Hydropower Development Co., Ltd. He added that even the tiniest cracks can compromise the durability of a dam and shorten its service life.

However, the Yebatan Hydropower Station dam has not shown any signs of cracks so far. The massive challenge of temperature control to prevent cracks during winter concrete pouring in cold, high-altitude areas has been overcome by their construction team.

Overcoming a perennial challenge

"Casting a concrete dam is more like baking a cake. Initially, raw materials are poured into a mold first, then the structure is allowed to take shape within that mold," said Du.

However, pouring a concrete dam is more complex due to natural constraints. During the process, the exterior cools rapidly while internal heat from cement hydration accumulates, causing stress due to temperature differences. Once the stress exceeds the endurance limit of the concrete, cracks will form.

Notably, renowned projects such as the Hoover Dam, Aswan Dam, and Itaipu hydropower station, all have the experience of forming cracks during construction. These cracks not only weaken structural integrity but also reduce the dam's capacity to bear pressure.

The construction of the Yebatan Hydropower Station faces a multitude of challenges, including extreme cold, high altitude, significant day-night temperature fluctuations, steep slopes, the complexities associated with building a high arch dam, elevated ground stress, and a climate characterized by long winters and brief transitional seasons between spring and autumn. These conditions make it far more difficult to avoid cracks altogether.

Temperature-controlled dam

The construction team knew that controlling the temperature was the key to building a dam with no cracks in the area.

The hyperbolic arch dam design increased the difficulty of controlling the temperature.

This kind of structure makes the dam subject to many constraints, so that the temperature change is easy to cause cracks to Appear.

"Traditional concrete crack prevention methods are almost ineffective. The low temperature causes the concrete to freeze quickly, seriously affecting the overall quality of the dam," said Zhong Fulin, one of Du's assistants.

After numerous tests and discussions, they produced an imaginative solution to build a controlled temperature area in the dam.

Zhong explained that in order to control temperature, they introduced Inflated Membrane Structure technology, which sprayed polyurethane, a coating material, on the upstream and downstream dam surfaces, and laid plastic films on the deck and cross peak surfaces to effectively maintain a wet environment. They also set up three layers of "insulation blankets" and added heating facilities such as hot heaters to ensure that the concrete can maintain a suitable temperature after pouring.

Self-monitoring operation

Other technologies are also needed to ensure that cracks don't appear in the dam.

"In the past, we relied on our experience to control the temperature, which is time-consuming and not accurate," said Liu Qiang, executive director of the Yebatan Branch.

Now, they rely on the intelligent temperature-control system to set up a "monitor" for the dam, which improves the efficiency of temperature control.The system can monitor the temperature change inside the dam in real-time. Once an anomaly is detected, it responds quickly and adjusts the state of the facility to ensure that the concrete that has been poured is always at the optimal temperature.

Besides, monitoring is also applied to the intelligent management of engineering construction. Through real-time integration of data, it realizes intelligent monitoring of the whole process from concrete production to vibration operation. In addition, it has set up a one-click operation and unmanned control of the grouting operation.

"These technologies allow the dam to remain crack free in extreme weather conditions," said Liu.

Editor:WANG Jing

Top News

Tapping Into China's Vast Opportunities

Two recent expos — the fifth edition of the China International Consumer Products Expo (CICPE) and the 137th edition of the China Import and Export Fair (the Canton Fair) — have once again solidified the country's role as a cornerstone of global commerce.

LLM Speeds Up High-altitude Research

QwQ-32B, a reasoning large language model (LLM) by Alibaba's Tongyi Qianwen (Qwen), has been integrated with the scientific research of several institutes of the Chinese Academy of Sciences (CAS), facilitating research on solar flare and water resources on the Qinghai-Xizang Plateau.

抱歉,您使用的瀏覽器版本過低或開啟了瀏覽器兼容模式,這會影響您正常瀏覽本網頁

您可以進行以下操作:

1.將瀏覽器切換回極速模式

2.點擊下面圖標升級或更換您的瀏覽器

3.暫不升級,繼續瀏覽

繼續瀏覽
主站蜘蛛池模板: 女神异闻录5在线观看 | 日本中文字幕一区二区有码在线 | 日韩一区二区视频在线观看 | 亚洲AV最新高清每天更新 | 日韩人妻中文无码一区二区 | 亚洲JIZZJIZZ中国少妇中文 | 久久99精品久久久久久秒播 | 中国亚洲女人69内射少妇 | av在线网站免费观看 | 欧美激情性a片在线观看不卡 | 中文字幕永久视频 | 欧美性成人 | 越做高潮越喷奶水视频 | 91麻豆精品在线 | 亚洲色大成网站www 久久久久91 | 欧美操日韩 | 欧美成ee人免费视频 | av色蜜桃一区二区三区 | 热久久综合网 | 四虎激情网 | 国产一区二区在线观看视频 | 青草免费| 91视频青娱乐 | 伊人狠狠| 亚洲成人av影片 | 琪琪宅男午夜视频 | 十八禁gay网站 | 亚洲毛片免费看 | 露脸国产精品自产拍在线观看 | 亚洲不卡av一区二区三区 | 麻豆国产精品视频 | 精国品产一区二区三区有限公司 | 婷婷成人综合激情在线视频播放 | 欧美阿v高清资源在线 | 国产亚洲美女视频 | 国产一级aaa毛片 | 一级片久久久久久 | 日本黄色影片在线观看 | 1769国内精品视频在线播放 | 日韩一区二区a片免费观看 法国性xxxx精品hd | 尤物网址在线观看 |